REVERTE

industrial-General-Contractor-Contratista-Trebotti-Mexico-Proyectos-llave-en-mano-turnkey-projects-REVERTE

The Brief.

  • Calcium Carbonate production plant divided in three phases IA-IB-IC, that include the construction of a primary crushing area, a storage room of 15,000 sq. ft., a production building of 130 ft. high and 16 storage silos.

The Plan.

  • Total execution time: 13 months (engineering-construction-startup).
  • 85,000 cu ft concrete.
  • 150 tons of reinforcement steel.
  • 22,000 sq. ft. concrete floors.
  • 1,500 Tons of metallic structure.
  • 20,000 sq. ft. of grid floors Irving type.
  • 9000 sq. ft. of metallic floors with skid plate.
  • 3,600 ft. of hand rails.
  • 57,000 sq. ft. of cover and facade sheet.
  • 334 tons of mounted equipment in more than 300 machines.
  • 1,500 ft. of belt conveyors.

industrial-General-Contractor-Contratista-Trebotti-Mexico-Proyectos-llave-en-mano-turnkey-projects-REVERTE

About This Project

  • 9 professionals at work (Engineers, Architects, Technicians).
  • Hand labor: monthly average of 98 people.